SECTION 155:30-5-1. Approval process for aggregator and verifier applications  


Latest version.
  •   Aggregators seeking to receive verification of carbon offsets and persons seeking to conduct verification of carbon offsets under this program must apply to and be approved by the Commission.
    (1)   Approval. The Commission shall notify the applicant in writing within ninety (90) days of receipt of an application that they have been approved to participate as an aggregator or verifier in the program.
    (2)   Denial. Any denial of an application shall be provided to the applicant in writing within ninety (90) days of receipt of an application, along with the reasons that the application was denied. A denial shall also advise the applicant of their right of appeal and of the procedures necessary to exercise those appeal rights.
    (3)   Withdrawal. Any application may be withdrawn by the applicant at any time prior to approval or denial in response to an application. An applicant may withdraw an application at anytime by submitting a written request to the Commission. The application will be automatically withdrawn upon receipt of the request by the Commission. Any fees paid in connection with any application that is later withdrawn under this section shall not be refunded to the applicant.
[Source: (For information about related emergency rules, see Editor’s Note at beginning of Chapter); Added at 26 Ok Reg 1388, eff 7-1-09]