SECTION 165:10-3-25. Completion Reports
Latest version.
- (a) Initial Completion Report. A Completion Report shall be filed with the Commission on Form 1002A within 60 days after completion of operations regardless of whether or not the well was completed as a dry hole, producer, injection, disposal, or service well. An operator who fails to file a complete and correct Form 1002A Completion Report within the allotted time limit may be fined up to $250.00.(b) Amended Completion Report. An amended Completion Report shall be filed with the Commission on Form 1002A within 60 days after completion of operations to reenter, re-complete and/or convert to injection or disposal well regardless of whether or not the well was completed as a dry hole, producer, injection, disposal, or service well.(c) No allowable without Completion Report. The Conservation Division shall not assign an allowable to a well without an up-to-date Completion Report on file with the Conservation Division.(d) A completion report for any well in a multi-well system shall reference the primary well. An amended completion report for the primary well in a multi-well system shall reference all other wells in the system.