SECTION 165:35-34-4. Commodity fuel supply competitive bidding procurement process for a term greater than five years


Latest version.
  • (a)   Pre-approval filing. When a Utility contracts for commodity fuel supply for self-generation of electricity for a term greater than five years, and seeks a pre-determination of prudence, the Utility shall file an application and receive the Commission's approval of the Utility's proposed Request for Proposal (RFP) Competitive Bidding Procurement Process prior to the Utility issuing the RFP. The evaluation and approval of the RFP shall contain, but not be limited to, the proposed bidding process, the evaluation process, consistency with the Integrated Resource Plan (IRP), and a determination of need for the proposed fuel supply. The evaluation and approval of the RFP may contain a consideration of opt-out provisions. The process shall focus on and result in the lowest reasonable cost for ratepayers. The request shall be processed as follows:
    (1)   An Independent Evaluator may be utilized pursuant to 165:35-34-4(b);
    (2)   The soliciting Utility shall file a cause for pre-approval of the RFP and will provide notice to the Commission and Attorney General to engage in the RFP approval process at least thirty (30) calendar days before issuing a request for pre-approval of the proposed RFP;
    (3)   The soliciting Utility shall prepare the initial draft of the RFP documents that, to the extent practicable, utilizes industry standard contractual terms and contains all expected material terms and conditions and a solicitation schedule;
    (4)   In addition to the information required by (3) of this Section, the RFP, at a minimum, shall identify clearly:
    (A)   Term and Renewals;
    (B)   Types and quantity of fuel being solicited;
    (C)   All price and non-price evaluation factors to be considered;
    (D)   Respective weight for each price and non-price evaluation factor;
    (E)   The Utility's preliminary analysis of desired delivery points or options as appropriate; and
    (F)   The extent to which a consideration of hedging and price volatility mitigation has been included in the RFP; and
    (5)   A Commission order approving or disapproving the RFP shall be issued in no more than 180 calendar days following the filing of the Utility's application.
    (b)   Independent evaluator.
    (1)   The Commission Staff or Office of the Attorney General may, at their discretion, file a request with the Commission for the assessment of specific costs, which shall be deemed recoverable costs associated with conducting the prudence review analysis, related to the retention of an Independent Evaluator to monitor the RFP and competitive bidding process. Notwithstanding the foregoing, the Commission, or the Attorney General shall retain an Independent Evaluator to monitor the RFP and competitive bidding process in the following instances: (i) when an affiliate of the Utility is anticipated to participate in the competitive bidding process; (ii) when the RFP and bid resulting there from is expected to have a material impact on the Utility's cost of providing electricity to its customers, or (iii) when it is anticipated that the Utility may participate as a bidder in the competitive bidding process. The Commission shall establish the minimum qualifications and requirements for an Independent Evaluator and ensure the Independent Evaluator is financially and substantively independent from any soliciting electric Utility or affiliate thereof, complaining entity, and any potential bidder.
    (2)   The Independent Evaluator will report to the Commission or the Office of the Attorney General.
    (3)   If the Independent Evaluator's conclusion is different from the conclusion of the soliciting Utility about the winning bidder(s), the Independent Evaluator and Utility may attempt to resolve such differences. In the event the Independent Evaluator and Utility cannot resolve their differences, the soliciting Utility will determine which bid(s) is successful. The Independent Evaluator shall submit its independent evaluation to the Commission.
    (4)   As part of its contract with the Independent Evaluator, the Commission shall require the Independent Evaluator, to enter into an agreement to keep all information confidential that pertains to the disclosure and use of any models, analytical tools, data, or other materials of a confidential or proprietary nature provided or made available by the soliciting Utility in conjunction with the competitive bidding process.
    (c)   Affiliate bidders' requirements.
    (1)   Each soliciting Utility affiliate that intends to bid shall disclose publicly, in writing, the names and titles of the members of the affiliate's "Bid Team." Each soliciting Utility shall disclose publicly, in writing, the names and titles of the members of its "Evaluation Team." A Bid Team develops the affiliate's bid and, to assure fairness, is not involved, directly or indirectly, in the evaluation or selection of bids. An Evaluation Team evaluates bids, selects the successful bidder and, to assure fairness, is not involved, directly or indirectly, in the development of the affiliate's bid.
    (2)   Each soliciting Utility and bidding affiliate shall assure that the Bid Team and the Evaluation Team and any member of either do not engage in any communications, either directly or indirectly, regarding the RFP or the competitive bidding process. For bidder and Commission assurance, the soliciting Utility and bidding affiliate shall execute an acknowledgement that the Utility and affiliate have not and will not in the future so communicate, other than to submit and receive the bid at the appropriate time. The Bid Team and Evaluation Team may communicate as part of a bidding technical conference of which potential bidders or all actual bidders, if bids have already been submitted, are given adequate notice and opportunity to attend.
    (3)   The Evaluation Team shall report to the Independent Evaluator, any contact or communications by any bidder, including the Bid Team, and advise the bidder any future contact must be directed to the Independent Evaluator. Bidders and the Evaluation Team may communicate as part of a bidding technical conference which potential bidders or all actual bidders, if bids have already been submitted, are given adequate notice and opportunity to attend.
    (d)   Evaluation of responses to the RFP.
    (1)   The evaluation of the responses to the RFP will proceed as follows:
    (A)   The soliciting Utility will evaluate all timely submitted bids to determine the lowest reasonable cost for fuel supply that results in the lowest reasonable cost with consideration given to all other bid terms outlined in the RFP; and
    (B)   The Commission, Attorney General, Independent Evaluator, and non-competitive representatives will be included in the evaluation of all bids submitted to the soliciting Utility pursuant to the provisions of the Protective Order. The soliciting Utility shall include within the RFP the time and place for the opening of the bids so that the Commission, Attorney General, the Independent Evaluator and non-competitive representatives may attend and monitor the opening of bids. Bids shall be opened by the soliciting Utility at the time and place so indicated in the RFP whether or not any or all of those parties are in attendance.
    (2)   All bids shall be evaluated on the basis of the bidder's final best offer. Bids will be evaluated on all relevant economic and non-economic factors. No bidder shall be permitted to unilaterally submit a refreshed bid prior to award unless all bidders are given a meaningful opportunity to submit a refreshed bid as a result of some material, documented change. The Independent Evaluator shall be charged with evaluating any such changes and ensuring that the changes are substantive and not an attempt to influence the final selection process in favor of a particular bidder.
    (3)   Should any bid be unclear to such extent that the lack of clarity could impact the outcome of the bidding, the soliciting Utility, Commission, Attorney General, Independent Evaluator and non-competitive representatives may request further information from any bidder regarding its bid, provided, any such communication between or among the soliciting Utility, Commission, Attorney General, Independent Evaluator and non-competitive representatives and bidder should be conducted through an open process in which the Utility, Independent Evaluator, Commission, Attorney General and noncompetitive representatives are given adequate notice and an opportunity to attend.
    (4)   In conducting the evaluation of the responses, the soliciting Utility shall not: waive or otherwise modify any evaluation factor or evaluation weight for any bidder.
    (e)   Bid award.
    (1)   The Utility shall submit its decision, rationale and analysis concerning the successful bid with the Commission, non-competitive representatives, the Independent Evaluator, and the Attorney General within 24 hours of the selection. The utility shall provide the non-winning bidders notice that they were not selected as the winning bid.
    (2)   The PUD Director, any unsuccessful bidder, the Independent Evaluator, Intervenors, or the Attorney General shall have two (2) business days following submission of the successful bid decision to file with the Commission a complaint challenging the Utility's adherence to the approved RFP and the resulting bid award.
    (3)   In the event of the filing of such a complaint, after notice to all parties and hearing, the Commission shall determine whether the Utility's decision reveals a clear departure from the criteria stated in the previously obtained waiver or the RFP Document in which event the bid award may not be pre-approved by the Commission.
    (4)   The Commission shall endeavor to hear the complaint in camera within three (3) business days of the filing of the complaint.
    (5)   The Commission shall endeavor to enter a final order within fifteen (15) calendar days of the initial bid award letter. If the Commission has not entered a final order within fifteen (15) calendar days, the winning bidder may be allowed to refresh their bid pursuant to the provisions of the RFP.
    (6)   The Commission shall endeavor to enter a final order no later than thirty (30) calendar days after the initial bid award.
    (7)   Upon determination of the successful bidder, the Utility and successful bidder shall promptly proceed to finalize contracts necessary to implement the bid.
    (8)   The final order, if awarding a pre-determination of prudence, will provide as follows:
    (A)   Purchases made according to the terms of the contract shall be deemed prudent;
    (B)   Variances from the terms of the contract shall be subject to additional prudence review and determination.
    (f)   Waiver. Prior to a utility taking competitive procurement action other than the competitive procurement processes set forth in this Subchapter, such Utility shall seek a waiver of all or any part of these competitive bidding rules by filing a cause with the Commission if the Utility will seek pre-approval.
[Source: Added at 29 Ok Reg 1541, eff 7-12-12; Amended at 31 Ok Reg 1030, eff 9-12-14; Amended at 36 Ok Reg 620, eff 7-25-19]