SECTION 165:40-5-30. Reactive power  


Latest version.
  • (a)   Producer will generate sufficient reactive power reasonably necessary to meet requirements of the service agreement.
    (b)   Cooperative/utility may request new capacity and/or reactive power rating for facility if it is reasonably apparent they are no longer correct.
    (c)   To the extent that producer's facility fails to achieve a power factor of at least eighty-five (85%) percent, producer shall pay for var support under the appropriate tariff.