Oklahoma Administrative Code (Last Updated: March 11, 2021) |
TITLE 165. Corporation Commission |
Chapter 40. Standard Terms of Purchases from Purchasers of 300 KW or Less |
Subchapter 5. Installation and Parallel Operation |
Part 1. PRODUCER'S WIRING AND INTERCONNECTION |
SECTION 165:40-5-9. Inspections and tests
Latest version.
- (a) The cooperative/utility shall have the right to inspect the producer's electric generating facilities, to be present at initial tests, to measure power factor at any time, to conduct such operating tests as are necessary to ascertain that the protective devises function properly, to review any data collected from such facilities at all reasonable times, and to independently monitor the aforesaid system and related energy regime.(b) The producer shall have the right to review and copy, at producer's expense, any data collected by the cooperative/utility.