SECTION 240:1-5-7. Monitoring of local project funding contracts


Latest version.
  •   The Commission will be responsible for monitoring all local project funding contracts awarded under these rules. The Commission will have the right to require the local project administrator to submit any reports deemed necessary for the award and administration of the contract, and the local project administrator will allow the LPF Auditor to audit any of its books and records that the auditor deems necessary in order to ensure that the purposes of the contract are being fulfilled and that all laws and rules are being adhered to. The LPF auditor will also have the right to conduct a physical inspection of any facilities or programs that are benefited or impacted by the local project funding contract.
[Source: Added at 20 Ok Reg 832, eff 5-12-03]