SECTION 252:100-8-7. Permit issuance  


Latest version.
  • (a)   Criteria for issuance. A permit, permit modification, or renewal may be issued only if the applicable requirements of 27A O.S. §§ 2-14-101 through 2-14-401; OAC 252:4-7; and this Chapter have been met and the DEQ has determined that the conditions of the permit provide for compliance with all applicable requirements and, for applications subject to OAC 252:100-8-8, that the requirements of that Section have been satisfied.
    (b)   Draft permits and notice thereof. See OAC 252:4-7. A statement that sets forth the legal and factual basis for the draft permit conditions (including references to the applicable statutory or regulatory provisions) shall accompany the draft permit.
    (c)   EPA review. See OAC 252:100-8-8.
    (d)   DEQ final action. See OAC 252:4-7 and 252:100-8-8 when applicable.
    (e)   Timeline for technical review and issuance. The DEQ shall take final action on each application for a permit within 18 months after beginning its technical review in accordance with OAC 252:4-7-4 through 252:4-7-12 and OAC 252:4-7-31; and OAC 252:100-8-4(b)(7).
[Source: Added at 11 Ok Reg 977, eff 1-14-94 (emergency); Added at 11 Ok Reg 2031, eff 5-26-94; Amended at 13 Ok Reg 1919, eff 7-1-96; Amended at 15 Ok Reg 2590, eff 6-25-98; Amended at 18 Ok Reg 1455, eff 6-1-01; Amended at 22 Ok Reg 1111, eff 6-15-05]