SECTION 252:205-21-2. Generator fees  


Latest version.
  • (a)   Disposal plan. The fee for a disposal plan for one or two waste streams is $100 per generator per year. Each additional waste stream is $50 per year. There is no disposal plan fee for emergency incidents under 252:205-13-1. Disposal plans shall be canceled if the fees are not paid after the second notification.
    (b)   Annual monitoring and inspection fee. Oklahoma generators shall pay an annual fee of $100, except small quantity generators who pay $25. There is no monitoring fee for generators who obtain one-time disposal plans issued under 252:205-5-1 for emergency cleanup or waste removal.
[Source: Added at 16 Ok Reg 244, eff 11-2-98 (emergency); Added at 16 Ok Reg 1819, eff 6-11-99]