Oklahoma Administrative Code (Last Updated: March 11, 2021) |
TITLE 252. Department of Environmental Quality |
Chapter 4. Rules of Practice and Procedure |
Subchapter 7. Environmental Permit Process |
Part 3. AIR QUALITY DIVISION TIERS AND TIME LINES |
SECTION 252:4-7-32. Air quality applications - Tier I
Latest version.
- (a) Minor facility permits. The following air quality authorizations for minor facilities require Tier I applications.(1) New permits. New construction, operating and relocation permits.(2) Modifications of permits.(A) Modification of a construction permit for a minor facility that will remain minor after the modification.(B) Modification of an operating permit that will not change the facility's classification from minor to major.(C) Extension of expiration date of a construction permit.(b) Part 70 source permits. The following air quality authorizations for Part 70 sources require Tier I applications.(1) New permits.(A) New construction permit for an existing Part 70 source for any change considered minor under 252:100-8-7.2(b)(1).(B) New operating permit that:(i) is based on a construction permit that was processed under Tier II or III, and 252:100-8-8, and(ii) has conditions which do not differ from the construction permit's operating conditions in any way considered significant under 252:100-8-7.2(b)(2).(2) Modifications of permits.(A) Modification of any operating permit condition that:(i) is based on the operating conditions of a construction permit that was processed under Tier II or III, and 252:100-8-8, and(ii) does not differ from those construction permit conditions in any way considered significant under 252:100-8-7.2(b)(2).(B) A construction or operating permit modification that is minor under 252:100-8-7.2(b)(1).(C) Extension of expiration date of a Part 70 source's construction permit with no or minor modifications.(c) Other authorizations. The following air quality authorizations require Tier I applications.(1) New, modified and renewed individual authorizations under general operating permits for which a schedule of compliance is not required by 252:100-8-5(e)(8)(B)(i).(2) Burn approvals.(3) Administrative amendments of all air quality permits and other authorizations.