Oklahoma Administrative Code (Last Updated: March 11, 2021) |
TITLE 252. Department of Environmental Quality |
Chapter 4. Rules of Practice and Procedure |
Subchapter 7. Environmental Permit Process |
Part 7. WATER QUALITY DIVISION TIERS AND TIME LINES |
SECTION 252:4-7-71. Water quality time lines
Latest version.
- The Water Quality Division shall technically review applications and issue or deny permits within the following periods of time:(1) Discharges, 401 Certifications, industrial wastewater other than discharge, pretreatment trust users, and sludge management plan - 180 days;(2) Public water supply and water pollution control construction - 90 days; and(3) UIC applications - 300 days.