SECTION 252:515-25-53. Contents of post-closure plan  


Latest version.
  •   The post-closure plan shall include, as a minimum:
    (1)   identification of site-specific post-closure activities with a detailed narrative description of how each is expected to be performed and a schedule for completing all activities;
    (2)   calculation of post-closure cost estimates in accordance with Subchapter 27 of this Chapter;
    (3)   a schedule for a minimum of quarterly inspections of the facility;
    (4)   procedures for:
    (A)   repairing and maintaining all surface drainage structures and on-site permanent improvements and equipment; and
    (B)   reworking or replacing any defective groundwater monitor wells and other defective monitoring equipment and installing new wells and equipment as required;
    (5)   procedures for maintaining the leachate collection system and collecting, treating and properly disposing of leachate;
    (6)   protocol for collecting and analyzing soil and water (surface and subsurface) samples as required;
    (7)   methods for maintaining site security and access control;
    (8)   procedures for:
    (A)   maintaining vegetation and other erosion controls in the post-closure area; and
    (B)   repairing erosion and maintaining final cover to meet the requirements of OAC 252:515-19-53, including the schedule for mowing and fertilizing final cover vegetation and other areas as needed;
    (9)   documentation of a legal right to enter, use, maintain, and monitor the facility throughout the post-closure period, in accordance with OAC 252:515-3-34;
    (10)   the outline for preparing the annual post-closure report in accordance with OAC 252:515-25-54(a)(2);
    (11)   the requirements for preparing a certification of post-closure performance in accordance with OAC 252:515-25-56;
    (12)   a description of the planned future uses, if any, of the property during the post-closure period; and
    (13)   a description of any other tasks necessary to accomplish adequate post-closure care.