SECTION 252:515-3-39. Additional information for used tire facilities  


Latest version.
  •   In addition to the requirements of OAC 252:515-3-36, permit applications for used tires facilities shall include the following:
    (1)   the intended development, tire processing equipment specifications, and detailed operational plans for the facility;
    (2)   how the facility will be visually screened, including the planting of trees and other vegetation;
    (3)   methods appropriate for the protection of human health and the environment to control on-site populations of rodents, flies, mosquitoes, or other animals or insects capable of transmitting disease to humans;
    (4)   the use of mosquito monitoring devices to determine the mosquito population, a determination of whether or not control action is warranted, and plans to implement control measures as necessary;
    (5)   the intended use for the processed tire material, consisting of a detailed statement about the owner/operator's plans to make the processed tire material available and accessible for recycling, reuse or energy recovery;
    (6)   a description of how the processed tire material will be disposed if the intended use ceases to be a viable option;
    (7)   a fire protection plan that includes:
    (A)   how the facility will respond to a fire and with what equipment;
    (B)   the criteria for calling the fire department;
    (C)   accessibility to a fire hydrant with sufficient water pressure to meet the facility's fire protection needs;
    (D)   how to control surface water run-off resulting from fire extinguishing efforts;and
    (E)   other relevant information;
    (8)   documentation from the local governmental entity responsible for supplying fire protection for the used tire facility, approving the facility's fire protection plan;
    (9)   plans for surface water run-off controls around tire piles and processed tire piles to prevent surface water runoff. Engineering plans shall also address discharge of run-off under an OPDES permit or diversion of collected runoff into a POTW or an evaporation pond;
    (10)   plans for a storage area that shall not contain more than 250,000 whole tires;
    (11)   plans to ensure all 77 counties of Oklahoma are serviced at least once each calendar quarter; and
    (12)   a description of how compliance with the requirements of Parts 3 and 5 of OAC 252:515-21 (relating to used tire facilities and transportation) will be achieved and maintained.
[Source: Added at 20 Ok Reg 1151, eff 6-1-03; Amended at 29 Ok Reg 1005, eff 7-1-12]