SECTION 252:517-3-35. Existing contour map
Latest version.
- (a) Required map. The permit application shall include a constructed map showing the topographic contours prior to any operations at the facility.(b) Contour intervals. The contour interval on the map shall not be greater than two feet.(c) Required details. The existing contour map shall show the location and quantities of surface drainage entering and exiting the facility, and the locations of all boreholes with their surface elevations.