Oklahoma Administrative Code (Last Updated: March 11, 2021) |
TITLE 252. Department of Environmental Quality |
Chapter 517. Disposal of Coal Combustion Residuals from Electric Utilities |
Subchapter 9. Groundwater Monitoring/Corrective Action |
SECTION 252:517-9-5. Detection monitoring program
Latest version.
- (a) Detection monitoring required. The owner or operator of a CCR unit must conduct detection monitoring at all groundwater monitoring wells consistent with this Section. At a minimum, a detection monitoring program must include groundwater monitoring for all constituents listed in Appendix A to this Chapter.(b) Monitoring frequency. Except as provided in paragraph (d) of this Section, the monitoring frequency for the constituents listed in Appendix A to this Chapter shall be at least semiannual during the active life of the CCR unit and the post-closure period. For existing CCR landfills and existing CCR surface impoundments, a minimum of eight independent samples from each background and downgradient well must be collected and analyzed for the constituents listed in Appendix A and B to this Chapter no later than October 17, 2017. For new CCR landfills, new CCR surface impoundments, and all lateral expansions of CCR units, a minimum of eight independent samples for each background well must be collected and analyzed for the constituents listed in Appendices A and B to this Chapter during the first six months of sampling.(c) Number of samples. The number of samples collected and analyzed for each background well and downgradient well during subsequent semiannual sampling events must be consistent with OAC 252:517-9-4(e), and must account for any unique characteristics of the site, but must be at least one sample from each background and downgradient well.(d) Alternative monitoring frequency. The owner or operator of a CCR unit may demonstrate the need for an alternative monitoring frequency for repeated sampling and analysis for constituents listed in Appendix A to this Chapter during the active life and the post-closure care period based on the availability of groundwater. If there is not adequate groundwater flow to sample wells semiannually, the alternative frequency shall be no less than annual. The need to vary monitoring frequency must be evaluated on a site-specific basis and approved by the DEQ. The demonstration must be supported by, at a minimum, the information specified in paragraphs (d)(1) and (2) of this Section.(1) Information documenting that the need for less frequent sampling. The alternative frequency must be based on consideration of the following factors:(A) Lithology of the aquifer and unsaturated zone;(B) Hydraulic conductivity of the aquifer and unsaturated zone; and(C) Groundwater flow rates.(2) Information documenting that the alternative frequency will be no less effective in ensuring that any leakage from the CCR unit will be discovered within a timeframe that will not materially delay establishment of an assessment monitoring program.(3) The owner or operator must obtain a certification from a qualified professional engineer stating that the demonstration for an alternative groundwater sampling and analysis frequency meets the requirements of this Section. The owner or operator must include the demonstration providing the basis for the alternative monitoring frequency and the certification by a qualified professional engineer in the annual groundwater monitoring and corrective action report required by OAC 252:517-9-1(e).(e) Statistically significant increase. If the owner or operator of the CCR unit determines, pursuant to OAC 252:517-9-4(h) that there is a statistically significant increase over background levels for one or more of the constituents listed in Appendix A to this Chapter at any monitoring well at the waste boundary specified under OAC 252-517-9-2(a)(2), the owner or operator must:(1) Except as provided for in paragraph (e)(2) of this Section, within 90 days of detecting a statistically significant increase over background levels for any constituent, establish an assessment monitoring program meeting the requirements of OAC 252:517-9-6, and have the assessment monitoring program approved by the DEQ.(2) The owner or operator may demonstrate that a source other than the CCR unit caused the statistically significant increase over background levels for a constituent or that the statistically significant increase resulted from error in sampling, analysis, statistical evaluation, or natural variation in groundwater quality. The owner or operator must complete the written demonstration within 90 days of detecting a statistically significant increase over background levels to include obtaining a certification from a qualified professional engineer verifying the accuracy of the information in the report. A report documenting this demonstration shall be submitted to the DEQ for approval. If a successful demonstration is completed within the 90-day period, the owner or operator of the CCR unit may continue with a detection monitoring program under this Section. If a successful demonstration is not completed within the 90-day period, the owner or operator of the CCR unit must initiate an assessment monitoring program as required under OAC 252:517-9-6. The owner or operator must also include the demonstration in the annual groundwater monitoring and corrective action report required by OAC 252:517-9-1(e), in addition to the certification by a qualified professional engineer.(3) The owner or operator of a CCR unit must prepare a notification stating that an assessment monitoring program has been established. The owner or operator has completed the notification when the notification is placed in the facility's operating record as required by OAC 252:517-19-1(h)(5).(f) Recordkeeping. The owner or operator of the CCR unit must comply with the recordkeeping requirements specified in OAC 252:517-19-1(h), the notification requirements specified in OAC 252:517-19-2(h), and the Internet requirements specified in OAC 252:517-19-3(h).