SECTION 252:623-5-4. Hauled wastewater


Latest version.
  • (a)   Septic tank waste may be introduced into the POTW only at locations designated by the CTT, and at such times as are established by the CTT. Such waste shall not violate Subchapter 1 or Subchapter 3 of this Chapter or any other requirements established by the DEQ. The DEQ may require septic tank waste haulers to obtain wastewater discharge permits.
    (b)   The DEQ shall require haulers of industrial waste to obtain wastewater discharge permits. The DEQ may require generators of hauled industrial waste to obtain wastewater discharge permits. The DEQ also may prohibit the disposal of hauled industrial waste. The discharge of hauled industrial waste is subject to all other requirements of this Chapter.
    (c)   Industrial waste haulers may discharge loads only at locations designated by the CTT. No load may be discharged without prior consent of the CTT. The CTT may collect samples of each hauled load to ensure compliance with applicable standards. The DEQ may require the industrial waste hauler to provide a waste analysis of any load prior to discharge.
    (d)   Industrial waste haulers must provide to the DEQ a waste-tracking form for every load. This form shall include, at a minimum, the name and address of the industrial waste hauler, permit number, truck identification, names and addresses of sources of waste, and volume and characteristics of waste. The form shall identify the type of industry, known or suspected waste constituents, and whether any wastes are RCRA wastes.
[Source: Added at 18 Ok Reg 1601, eff 6-1-01]