SECTION 252:633-3-21. Building phase submittals  


Latest version.
  •   The following submittal and accompanying actions by the recipient are required during and upon the completion of the construction of the project;
    (1)   Any change order shall be submitted to the DEQ for approval;
    (2)   Once construction is completed, notice shall be submitted to the DEQ; and
    (3)   A complete set of as-built drawings shall be submitted to the DEQ upon completion of construction.
[Source: Added at 14 Ok Reg 1139, eff 3-18-97 (emergency); Added at 14 Ok Reg 1690, eff 6-2-97; Amended at 15 Ok Reg 1957, eff 6-1-98; Amended at 25 Ok Reg 1140, eff 7-1-08]