Oklahoma Administrative Code (Last Updated: March 11, 2021) |
TITLE 252. Department of Environmental Quality |
Chapter 653. Aquifer Storage and Recovery |
Subchapter 1. General Provisions |
SECTION 252:653-1-12. Fees
Latest version.
- (1) ASR Treatment Plant Construction Permit - $3,000(2) ASR Water Delivery Construction Permit - $10,000(3) ASR Operations Permit - $10,000(b) Annual operating fee. The annual operating fee for an ASR facility, permitted under Subchapter 9 of this Chapter, is $5,000 per year due on the anniversary of permit issuance.