Oklahoma Administrative Code (Last Updated: March 11, 2021) |
TITLE 252. Department of Environmental Quality |
Chapter 653. Aquifer Storage and Recovery |
Subchapter 9. Aquifer Storage & Recovery Operations |
SECTION 252:653-9-10. Groundwater monitoring requirements
Latest version.
- (a) Groundwater monitoring. The permittee shall monitor the groundwater quality through a network of groundwater monitoring wells for site-specific constituents to be approved by DEQ.(b) Alert triggers. The applicant shall identify alert triggers, to be approved by DEQ, for each constituent monitored, for which the contingency plan will be activated.(c) Frequency. DEQ shall approve groundwater monitoring frequency on a case-by-case basis.(d) Submittal of data to DEQ. All groundwater monitoring data required by this Subchapter shall be submitted to DEQ.