SECTION 252:653-9-2. Duration and continuation of expiring permit  


Latest version.
  • (a)   Any ASR operating permit issued under this Subchapter shall extend for a period of (10) ten years, and shall be reviewed by DEQ every (5) five years for possible permit modification. Upon expiration of an ASR operating permit, a permittee may seek a renewal in accordance with the application requirements of this Subchapter.
    (b)   A permittee may continue operating under the conditions of an expired permit provided that a permit renewal application has been submitted to DEQ 180 days prior to expiration of the permit.
    (c)   In the event that the water quality standards of OAC 785:45 change within the duration of an ASR operating permit, the permittee shall submit a plan within 180 days of the effective date of the standard to ensure the continued operation of the ASR project shall meet the new water quality standards.
[Source: Added at 35 Ok Reg 1333, eff 9-15-18]