SECTION 25:40-3-2. Final Documentation from the Federal Aviation Administration and Department of Defense


Latest version.
  • (a)   The owner of a wind energy facility shall submit to the Aeronautics Commission the Determination of No Hazard from the FAA for each individual wind turbine or other individual structure that requires a 7460-1 form that is part of a wind energy facility prior to the start of construction.
    (b)   The owner of a wind energy facility shall submit to the Aeronautics Commission the Military Compatibility Certification Letter or successor form from the Clearinghouse which serves as documentation of the resolution of adverse impacts to the Department of Defense prior to the start of construction.
    (c)   All submissions shall be submitted electronically unless prior approval of another format has been granted by the Director.
[Source: Added at 37 Ok Reg 823, eff 11-15-19 (emergency); Added at 37 Ok Reg 941, eff 9-11-20]