SECTION 260:65-1-20. Contract completion  


Latest version.
  •   A Certificate of Contract Completion shall be prepared by the design consultant using the form prescribed by the Department. The contractor shall complete the Contractor's Affidavit on all required copies of the Certificate of Contract Completion and return to the design consultant. The total of the contract shown on the certificate shall include the sum of all change orders. The contractor shall secure and transmit to the design consultant a completed and notarized Consent of Surety with the contractor's Certificate of Final Payment. All submittals, operating manuals, brochures, as-built drawings, receipts for keys given to the using agency, warranties, and all other requirements of the contract shall have been submitted to the design consultant with signed receipts from the using agency for the items received by them, before final payment is made.
[Source: Added at 31 Ok Reg 1423, eff 9-12-14]