SECTION 260:65-19-8. Selection Procedure for design consultant for design-build  


Latest version.
  • (a)   The state agency shall select a design consultant pursuant to provisions of Subchapter 3 of this Chapter.
    (b)   The state agency shall develop, with the assistance of the design consultant, a comprehensive scope of work statement and design criteria package that defines the project. This package will be issued to competing design-build teams, enabling the design-builders to submit proposals that meet the state agency's needs. The scope of work/design criteria package should contain, but not be limited to, the following information:
    (1)   A conceptual design including, as a minimum, a space plan and programmatic summary of state agency's requirements.
    (2)   Topographic survey and existing utility systems survey information for the project site.
    (3)   Geotechnical report of soils conditions for the project site.
    (4)   Clear definition of type of building desired, quality of materials, finishes, etc.
    (5)   Disclosure of the construction price limit of the project so firms don't run the risk of preparing proposals that are not price competitive.
[Source: Added at 31 Ok Reg 1423, eff 9-12-14]