SECTION 300:35-13-6. Expiration of permit


Latest version.
  • (a)   Any project permitted pursuant to Subchapter 13 of these rules must be completed within two (2) years from either the date the permission to construct or modify is issued by GRDA or the date the Federal Energy Regulatory Commission issues an order approving the action, whichever occurs later.
    (b)   Prior to the expiration of the dredging permit, upon written request of the permit holder, the GRDA Board of Directors may extend the time in which such dredging activities must be completed.
    (c)   If the permit expires, the permit is null and void.
[Source: Added at 23 Ok Reg 1329, eff 5-25-06; Amended at 27 Ok Reg 1801, eff 6-25-10; Amended at 30 Ok Reg 1121, eff 6-27-13; Amended at 34 Ok Reg 1265, eff 9-11-17]