SECTION 35:30-17-68. Soil treatment outside of building  


Latest version.
  •   The exterior soil along the foundation or veneer wall shall be trenched or trenched and rodded through the bottom of the trench. Treatment of the backfill of the trench is permitted. Rod holes shall not be spaced more than twelve inches (12") apart. The size of the trench shall be consistent with product label requirements.
    (1)   Where the footing is exposed at ground level, trench or trench and rod through the bottom of the trench along the outside edge of the footing.
    (2)   Where trenching or trenching and rodding is not possible due to presence of masonry walls, gutters, terraces, sidewalks, and other similar locations, holes shall be drilled at not more than twelve inch (12") intervals and the soil shall be treated adjacent to the structure.
[Source: Amended at 12 Ok Reg 3408, eff 7-11-95 (emergency); Amended at 13 Ok Reg 1863, eff 6-14-96; Amended at 17 Ok Reg 1018, eff 5-11-00; Amended at 27 Ok Reg 2441, eff 7-25-10]