Oklahoma Administrative Code (Last Updated: March 11, 2021) |
TITLE 460. Department of Mines |
Chapter 20. The Permanent Regulations Governing the Coal Reclamation Act of 1979 |
Subchapter 45. Permanent Program Performance Standards: Underground Mining Activities |
SECTION 460:20-45-56. Interpretative rules related to general performance
Latest version.
- The following interpretations of rules promulgated in Subchapter 45 of this Chapter have been adopted by the Oklahoma Department of Mines.(1) [Reserved] and(2) [Reserved](3) Interpretation of Section 460:20-45-7(4) Topsoil removal.(A) Results of physical and chemical analyses of overburden and topsoil to demonstrate that the resulting soil medium is equal to or more suitable for sustaining revegetation than the available topsoil, provided that trials and tests are certified by an approved laboratory in accordance with Section 460:20-45-7, may be obtained from any one or a combination of the following sources:(i) U.S. Department of Agriculture Soil Conservation Service published data based on established soil series;(ii) U.S. Department of Agriculture Soil Conservation Service Technical Guides;(iii) State agricultural agency, university, Tennessee valley Authority, Bureau of Land Management or U.S. Department of Agriculture Forest Service published data based on soil series properties and behavior; or(iv) Results of physical and chemical analyses, field site trials, or greenhouse tests of the topsoil and overburden materials (soil series) from the permit area.(B) If the operator demonstrates through soil survey or other data that the topsoil and unconsolidated material are insufficient and substitute materials will be used, only the substitute materials must be analyzed in accordance with Section 460:20-45-7.(5) Interpretation of Section 460:20-45-51: Postmining land use.(A) The requirements of Section 460:20-31-8 (a) (2) of this Chapter, for approval of an alternative postmining land use, may be met by requesting approval through the permit revision procedures of Section 460:20-17-3 of this Chapter rather than requesting such approval through the permit application. The original permit application, however, must demonstrate that the land will be returned to its premining land use capability as required by Section 460:20-45-51(a). An application for a permit revision of this type:(i) Must be submitted in accordance with the filing deadlines of Section 460:20-17-3 of this Chapter,(ii) Shall constitute a significant alteration from the mining operations contemplated by the original permit, and(iii) Shall be subject to the requirements of Subchapters 15 and 19 of this Chapter.