Oklahoma Administrative Code (Last Updated: March 11, 2021) |
TITLE 460. Department of Mines |
Chapter 25. Oklahoma Explosives and Blasting Rules and Regulations |
Subchapter 13. Performance Standards |
SECTION 460:25-13-17. Blasting plan
Latest version.
- (a) Each permitted blasting operation shall be conducted pursuant to a blasting plan and the blasting plan shall include at a minimum the following information;(1) Types and appropriate amounts of explosives to be used for the type of blasting operation to be conducted;(2) Description of procedures and plans for recording and retention of information during blasting; and(3) Description of blasting warnings and site access control equipment and procedures.(b) The blasting plan shall be submitted to the Department at least seven days before the blast or 48 hours after the blast in emergency situations.