SECTION 752:11-5-5. Award of contract  


Latest version.
  •   Contracts may be standard or non-standard depending on the project. Services may include all or any of the following depending on the size and type of project.
    (1)   Program planning, which may include the following:
    (A)   Space plan.
    (B)   Written and/or graphic program document as specified.
    (C)   Circulation allowances.
    (D)   Cost estimate.
    (2)   Schematic design, which may include the following:
    (A)   The line drawing and graphic representation of the floor plan, perspective drawings, and site orientation of the project.
    (B)   Energy and feasibility presentation of utility access, recommended materials, parking, traffic flow, site access, and space and volume estimates of cost.
    (C)   Cost estimate.
    (3)   Design development. A set of drawings may be required to be produced which specifies the project's specified parameters, resulting in:
    (A)   The site plan for parking, street and pedestrian access.
    (B)   Overall dimensions.
    (C)   Rooms and traffic circulation within the buildings.
    (D)   Types of materials.
    (E)   Building elevations.
    (F)   Building sections.
    (G)   Recommended structural systems.
    (H)   Recommended mechanical systems and equipment based upon life cycle studies.
    (I)   Cost estimate.
    (4)   Construction phase services. The consultant may be required to perform specific construction phase services which include:
    (A)   Review and approval of shop drawings.
    (B)   Review and approval of pay requests.
    (5)   All standard contracts shall include a reference to construction monitoring which is periodic visits at intervals appropriate to the stage of the contractor's operations, by the consultant to the construction site to determine that the contractor is following the intent of the construction contract.
    (6)   Changes to the consultant's base contract may be approved by the CFMO as long as the scope of the change is generally included within the project description developed at 752:11-5-2(a) for which the consultant selection process was conducted. Changes must reference the correct contract and include the scope of the change, the fee for the change, and the source of the funding for the change. Changes to the consultant's base contract shall not result in fees that would exceed the caps set by 752:11-5-4(c)-(d).
[Source: Added at 36 Ok Reg 1970, eff 9-18-19]