SECTION 752:11-7-15. Substantial completion inspection  


Latest version.
  • (a)   This inspection is to be requested by the contractor after he has determined that the project is substantially complete. Substantial completion is defined as the construction is sufficiently completed in accordance with the plans and specifications, as modified by any authorized changes, so that the owner can occupy the building and/or use the facility for its intended use.
    (b)   After receipt of a list of items to be completed or corrected from the contractor, the inspection is to be scheduled by the CFMO or his designee and/or Design Consultant who shall send out written notification inviting the ADC and other interested persons to attend. After the inspection, the Certificate of Substantial Completion Form with punch list shall be prepared by the CFMO or his designee and/or Design Consultant. A time limit to complete the punch list of deficiencies shall be determined by the Contractor and approved by the CFMO or his designee and/or Design Consultant. Two (2) copies of the form shall be provided to the Authority for signature.
[Source: Added at 36 Ok Reg 1970, eff 9-18-19]