SECTION 752:11-7-9. Construction conference  


Latest version.
  • (a)   A construction conference may be called periodically by, when applicable, the CFMO or his designee or the Design Consultant to discuss:
    (1)   Project progress as it relates to schedule.
    (2)   Payment requests and their status.
    (3)   Change order requests and their status.
    (4)   Special problems and remedial action required.
    (5)   Results of previous remedial action.
    (6)   Other subjects as required.
    (b)   The meeting shall be chaired by the CFMO or his designee or the Design Consultant. Minutes of the meeting shall be kept, typed, and distributed to all applicable parties within five (5) working days.
[Source: Added at 36 Ok Reg 1970, eff 9-18-19]