SECTION 785:25-7-4. Supervision of construction by owner
Latest version.
- After receiving approval of plans and specification, supervision of construction by the owner shall be as follows:(1) The work of construction, enlargement, repair, alteration or removal of dam or reservoir, for which approved application, plans, drawings, and specifications are required, shall be under the responsible charge of an engineer as defined in 785:25-5-2 who shall certify, upon completion and prior to impoundment of any waters, that such construction, enlargement, repair, alteration, or removal was done in accordance with approved plans, drawings, and specifications.(2) Final approval in writing by a United States governmental agency shall be required for those structures designed by and/or constructed under the supervision of personnel of that agency.