Oklahoma Administrative Code (Last Updated: March 11, 2021) |
TITLE 785. Oklahoma Water Resources Board |
Chapter 25. Dams and Reservoirs |
Subchapter 9. Actions After Construction |
SECTION 785:25-9-11. Upgrading dams due to downstream development
Latest version.
- (a) Alternatives. Instead of upgrading the dam using structural methods, an owner may seek to implement alternative methods. Such alternative methods shall include but is not limited to the following:(1) a current breach analysis and hydrologic study that demonstrates a lesser hazard-potential classification is correct; or(2) a current breach analysis and design flood analyses that demonstrate existing downstream developments would not be adversely affected by more than one foot difference between breach and non-breach simulations in the affected area, or records showing the downstream development has been dedicated to non-residential and non-commercial use; or(3) a plan to permanently remove the dam.(b) Schedule of Compliance. An owner may seek a compliance schedule with the Board that sets the timeframes for various stages of work to be performed. In considering such applications to upgrade on a compliance schedule the Board shall evaluate whether the current dam will not significantly affect the public safety during the compliance period.