Chapter 11. Acquisitions and Construction  


Subchapter 1. General Provisions
SECTION 752:11-1-1. Purpose
SECTION 752:11-1-2. Definitions
SECTION 752:11-1-3. General provisions
SECTION 752:11-1-4. Ethics
SECTION 752:11-1-5. Online bidding [74 O.S. § 85.45r]
Subchapter 3. Purchasing
SECTION 752:11-3-1. Supplier selection and standard requirements
SECTION 752:11-3-2. Acquisitions
SECTION 752:11-3-3. Formal or Informal Competitive Solicitations ($5,000 - $50,000)
SECTION 752:11-3-4. Competitive sealed solicitations ($50,000+)
SECTION 752:11-3-5. Bid submission
SECTION 752:11-3-6. Bid changes and withdrawal
SECTION 752:11-3-7. Non-responsive bids.
SECTION 752:11-3-8. Contract negotiation and award
SECTION 752:11-3-9. Contract management
SECTION 752:11-3-10. Acquisitions by facilities management and housekeeping contractor
SECTION 752:11-3-11. Professional service contracts
SECTION 752:11-3-12. Sole source contracts
SECTION 752:11-3-13. Emergency acquisitions
SECTION 752:11-3-14. Credit/debit card
Subchapter 5. Design Consultants
SECTION 752:11-5-1. Registration of Design Consultants
SECTION 752:11-5-2. Selection procedure
SECTION 752:11-5-3. Scheduling and performing interviews
SECTION 752:11-5-4. Negotiation of contract
SECTION 752:11-5-5. Award of contract
SECTION 752:11-5-6. Professional services contracts
Subchapter 7. Construction
SECTION 752:11-7-1. Bid solicitations
SECTION 752:11-7-2. Bid documents
SECTION 752:11-7-3. Bid submittal
SECTION 752:11-7-4. Modifications/withdrawal of bids
SECTION 752:11-7-5. Bid openings
SECTION 752:11-7-6. Bid review and evaluation
SECTION 752:11-7-7. Contract award
SECTION 752:11-7-8. Pre-construction conference
SECTION 752:11-7-9. Construction conference
SECTION 752:11-7-10. Construction requirements; reviews and permits
SECTION 752:11-7-11. Adopted codes
SECTION 752:11-7-12. Payment requests
SECTION 752:11-7-13. Change orders
SECTION 752:11-7-14. Time extensions
SECTION 752:11-7-15. Substantial completion inspection
SECTION 752:11-7-16. Final inspection
SECTION 752:11-7-17. Contract completion
Subchapter 9. Construction Management/At Risk
SECTION 752:11-9-1. Registration of Construction Managers
SECTION 752:11-9-2. Project designation consideration
SECTION 752:11-9-3. Selection procedure
SECTION 752:11-9-4. Selection committee
SECTION 752:11-9-5. Scheduling and performing interviews
SECTION 752:11-9-6. Fee negotiation and contracts
SECTION 752:11-9-7. Award of contract
SECTION 752:11-9-8. Changes to base contract
Subchapter 11. Best Value Methodology
SECTION 752:11-11-1. Best Value vendor selection
SECTION 752:11-11-2. Vendor selection
SECTION 752:11-11-3. Clarification period
SECTION 752:11-11-4. Risk minimization and performance
SECTION 752:11-11-5. Transparency and Best Value documentation
SECTION 752:11-11-6. Other requirements for contracts awarded using Best Value methodology
Subchapter 13. Supplier Protests
SECTION 752:11-13-1. Supplier notification
SECTION 752:11-13-2. Review and determination
SECTION 752:11-13-3. Supplier appeal of decision to deny protest
SECTION 752:11-13-4. Determination
SECTION 752:11-13-5. Administrative procedure
SECTION 752:11-13-6. Remedies
SECTION 752:11-13-7. Decision to be final

Note


[Authority: 63 O.S., § 3208(B)(1)]
[Source: Codified ed-9-18]