SECTION 252:515-23-54. Tests  


Latest version.
  • (a)   Routine periodic tests. The incinerator design must provide sample injection and collection ports to enable the owner/operator or the DEQ to conduct periodic tests.
    (b)   Demonstration. Prior to operation, the owner/operator must conduct a demonstration showing complete destruction of a chemical which requires 2000oF for destruction and which is introduced into the unit under normal operating procedures.
[Source: Added at 20 Ok Reg 1151, eff 6-1-03]