SECTION 252:515-9-151. Required actions for implementation of corrective action  


Latest version.
  •   Based on the schedule for remedial activities approved in accordance with OAC 252:515-9-132(4):
    (1)   a groundwater monitoring program must be established and implemented as specified by the DEQ;
    (2)   the corrective action remedy selected must be implemented;
    (3)   interim measures necessary to ensure the protection of human health and the environment must be taken; and
    (4)   alternate measures for control, removal or decontamination of the sources of contamination must be implemented.
[Source: Added at 20 Ok Reg 1151, eff 6-1-03]