  • (a)   Lagoon inlet line. The lagoon inlet line shall:
    (1)   be made of solid pipe that complies with the minimum specifications listed in Appendix C;
    (2)   terminate in the center of the lagoon;
    (3)   be anchored and supported; and
    (4)   discharge onto a concrete structure that is a minimum of one (1) square foot.
    (b)   Septic tank outlet. For gravity flow systems, the outlet of the septic tank shall be at least six feet (6') above the bottom of the lagoon.
[Source: Added at 16 Ok Reg 1895, eff 6-11-99; Amended at 21 Ok Reg 1618, eff 6-11-04; Amended at 25 Ok Reg 2318, eff 7-11-08; Amended at 37 Ok Reg 1296, eff 9-15-20]