Oklahoma Administrative Code (Last Updated: March 11, 2021) |
TITLE 380. Department of Labor |
Chapter 25. Boiler and Pressure Vessel Rules |
Subchapter 3. Administration |
SECTION 380:25-3-3. Notification of inspection
Latest version.
- Certificate inspection, as required in Section 380:25-3-2, shall be scheduled prior to the expiration date of the certificate. External inspections may be performed by the Inspector during normal business hours and without prior notification. When as a result of an external inspection or a determination by other objective means, it is the Inspector's opinion that continued operation of the boiler or pressure vessel constitutes a menace to public safety, the Inspector may request an internal inspection or an appropriate pressure test or both to evaluate conditions. In such instances the owner or user shall prepare the boiler or pressure vessel for such inspections or test as the Inspector designates.