SECTION 380:50-25-1. Contractor fee
Latest version.
- (1) One thousand dollars ($1000.00) for each separate containment area of any asbestos abatement project.(2) For projects which are not a part of a definite containment area, or are performed with multiple glovebags or miniature containments, a fee of Three Hundred Fifty Dollars ($350.00), plus Ten Dollars ($10.00) per such glovebag or miniature containment, shall be paid.(3) Abatement projects which are undertaken by an owner or agent of an owner as a part of an operation and maintenance program under Section 380:50-14 shall be charged a fee of Two hundred fifty dollars ($250.00) per month for any month in which abatement took place. Failure to pay the required fee will void the operation and maintenance program, making subsequent abatement fall under the full scope of this Chapter.