Oklahoma Administrative Code (Last Updated: March 11, 2021) |
TITLE 460. Department of Mines |
Chapter 10. Non-Coal Rules and Regulations |
Subchapter 31. Blasting and Use of Explosives |
SECTION 460:10-31-9. Seismographic measurements
Latest version.
- (a) Where a seismograph is used to monitor the velocity of ground motion and the peak particle velocity limit of 1 inch per second is not exceeded, the equation in Section 460:10-31-8(j) need not be used. If that equation is not used by the operator, a seismograph record shall be obtained for each shot.(b) The use of a modified equation to determine maximum weight of explosives per delay for blasting operations at a particular site, may be approved by the Department, on receipt of a petition accompanied by reports including seismograph records of test blasting on the site. In no case shall the Department approve the use of a modified equation where the peak particle velocity of 1 inch per second required in Section 460:10-31-8(g) would be exceeded.(c) The Department may require a seismograph record of any or all blasts and may specify the location at which such measurements are taken.