SECTION 25:40-3-1. Notification of intent to build a wind energy facility and other notices  


Latest version.
  • (a)   The owner of a wind energy facility shall submit to the Aeronautics Commission copies of all initial FAA 7460-1 form(s) for all individual wind turbines or any other individual structure that requires a FAA form 7460-1 that is part of a wind energy facility within thirty (30) days of the initial filing with the FAA.
    (b)   If the owner of a wind energy facility is required to file subsequent 7460-1 forms with the FAA due to changing locations or heights of individual structures from the locations or heights originally proposed in the initial 7460-1 forms submitted to the Aeronautics Commission, the owner shall, within ten (10) calendar days of filing with the FAA, submit such subsequent 7460-1 forms to the Aeronautics Commission.
    (c)   The 7460-1 form(s) shall be submitted electronically unless prior approval of another format has been granted by the Director. A cover letter shall accompany the 7460-1 form(s) detailing the name of the project, the owner of the wind energy facility, and indicating whether the submittal is for initial 7460-1 form(s) or subsequent 7460-1 form(s).
[Source: Added at 37 Ok Reg 823, eff 11-15-19 (emergency); Added at 37 Ok Reg 941, eff 9-11-20]